Title 13 (selected sections)
Chapter 13.10 STORM AND SEWER SURFACE WATER UTILITY
Section 13.10.010 Definitions.
A. Authorized City Official. For the purposes of this chapter, the
Anacortes director of public works or designee may be cited herein as only
"official" for simplicity of presentation.
B. "Developed parcel" means any parcel which has been altered by
grading or filling of the ground surface, or by construction of any
improvement or other impervious surface area which affects the hydraulic
properties of the parcel.
C. "Development" means any artificial change to property, including
but not limited to building or other structures, mining, dredging, filling,
all land-disturbing activities, clearing, grading, landscaping, paving,
excavation, or drilling operations.
D. "Drainage facility" means structures or features, natural or
artificial, that convey, treat, and/or abate surface water runoff, including
but not limited to detention facilities, retention facilities, and drainage
retention/abatement facilities.
E. "Equivalent residential unit (ERU)" or "Impervious surface unit (ISU)"
means a configuration of impervious which is approximately equal to that of
the average single family residential parcel. One ERU or ISU is equivalent
to two thousand square feet of impervious surface area.
F. "Impervious areas" means a hard surface area which either prevents
or retards the entry of water into the soil mantle and/or causes water to
run off the surface in greater quantities or at an increased rate of flow
from that present under natural conditions. Impervious surfaces may include,
but are not limited to, rooftops, concrete or asphalt paving, graveled
areas, walkways, patios, driveways, parking lots or storage areas, and
oiled, macadam or other surfaces which similarly impede the natural
infiltration or runoff of surface water.
G. "Parcel" means a separately segregated unit or plat of land having
an identified owner and specified boundaries.
H. "Residential parcel" means any parcel of land having on it a
single structure which is designed for occupancy by a single family or a
duplex residential unit.
I. "Undeveloped parcel" means any parcel which has not been altered
by construction of any improvements or other impervious surface areas which
affect the hydraulic properties of the parcel or by grading or filling. (Ord.
2488 § 1, 1999)
Section 13.10.020 System of charges.
A. There is imposed a system of charges on each developed parcel of
real property within the city to operate the stormwater program. The charges
are deemed reasonable and necessary to fund administration, planning,
design, construction, operation, maintenance, repair, improvement and
replacement of all existing and future storm and surface water facilities,
including the accumulation of reserves and the retirement of any associated
debt.
B. The following charges are established for all developed parcels of
real property in the city. The charges for all such parcels shall be
computed by multiplying the basic charge for each ISU times the total number
of ISUs per parcel.
1. General Facilities Charge. A one-time charge of one thousand one
hundred twenty-six dollars per ISU for new development for the planning,
design, and construction of capital improvements associated with the city
stormwater drainage system and facilities.
2. Monthly User Fee. The minimum monthly fee shall be three dollars/ISU,
and shall fund the operation, maintenance and administration of the city
stormwater utility.
3. Single Family and Duplex Residential Parcels. The charge shall be
one ISU per month for each single family or duplex residential parcel.
4. Undeveloped Parcels. Undeveloped parcels shall not be assessed a
GFC or monthly user fee.
5. Other Parcels (Commercial, Industrial, and Multi-family). The
charge for all parcels, except single-family and duplex residential parcels
and undeveloped parcels, shall be based upon the total amount of impervious
area as expressed in ISU. ISUs shall be measured for rate of computation
purposes to the nearest one-tenth of an ISU. The minimum charge shall be for
one ISU for a GFC or monthly user fee.
C. No monthly user fee shall be payable under subsection (B) of this
section for the area annexed to the city by Ordinance No. 2475 (effective
3/2/99) until 10/1/2002.
D. The monthly user fee in the HM and LM1 zones shall be twenty
percent of the standard city stormwater fee.
E. The general facilities charge (GFC) in the HM and LM1 zones shall
be twenty percent of the standard city GFC. (Ord. 2601, 2002; Ord. 2599,
2002; Ord. 2596, 2002; Ord. 2488 § 2, 1999)
Section 13.10.030 Billing and collection.
Storm and surface water charges for each parcel of real property within
the city shall be computed on a monthly basis. The amount billed shall be
included on the sanitary sewer bill or on the water or garbage bill if not
serviced by sanitary sewer. A separate billing may be made to those property
owners of developed parcels within the city who are not city of Anacortes
water, garbage, or sanitary sewer customers. (Ord. 2488 § 3, 1999)
Section 13.10.040 General facilities charges.
A one-time GFC of one thousand one hundred twenty-six dollars per ISU
shall be assessed for all new development of real property in the city,
except for new developments that make special arrangements acceptable to the
city public works director and federal and state agencies to undertake
direct discharge to marine waters. The GFC shall represent a fair and
equitable share of the historic and future cost of the city's storm and
surface water system of drainage structures and facilities. (Ord. 2488 § 4,
1999)
Section 13.10.050 Developer contributions.
The city is authorized to assess developers of real property within the
city a fair and equitable prorata portion of specific offsite storm and
surface water drainage improvements necessitated by new developments on
parcels owned by such developers. These assessments shall be made in
addition to any other requirements of the city for onsite improvements and
adjusted by the previous payment for a stormwater GFC for the parcel. All
developer contributions shall be placed in a separate revenue account and
earmarked for specific projects or improvement, and utilized solely for such
purposes. (Ord. 2488 § 5, 1999)
Section 13.10.060 Permits.
A permit is required for any person to construct, install, place, or
attempt to construct, install, or place any storm or surface drainage
structure or facility within the city. Every person desiring to construct or
install any storm or surface water facility, whether on private or public
property shall make application for same to the city prior to commencing
work on such project. Such applications shall be made on forms provided by
the city and shall include all information as may be required by the city.
The application shall be approved by the city official or his/her designate
prior to construction. Such construction or installation must comply with
all city ordinances, regulations, other controls or standards. Each
application submitted to the city shall be accompanied with payment for a
construction permit fee in an amount established by the city. Failure to
obtain such a permit will result in the fee doubled. Such fees shall defray
the cost of all inspections and plan review(s) required by the city prior to
and during the construction of storm and surface water drainage facilities.
This section shall not be construed to duplicate any other existing city
requirements. (Ord. 2488 § 6, 1999)
Section 13.10.070 Appeals.
Any owner or owners who dispute the amount of their charges or who
dispute any determination made by or on behalf of the city pursuant to and
by authority of this chapter, may petition the city official in writing for
a hearing on a revision or modifications of such charge or determination no
later than thirty days after having been billed for such charge or after
having been notified of such determination. Upon receiving such a petition,
the city official shall schedule a hearing within thirty days before the
city council. Notice of the hearing shall be provided to the petitioner at
least ten days prior to the hearing. Following the hearing, a final
determination shall be made by the city council and the petitioner so
notified within thirty days. (Ord. 2488 § 7, 1999)
Chapter 13.36 DRAINAGE REQUIREMENTS AND REGULATIONS
Section 13.36.010 Purpose.
The city council finds that this chapter is necessary to promote sound
development policies and construction procedures which respect and preserve
the city's watercourses; to minimize water quality degradation and control
of sedimentation of creeks, streams, ponds, lakes, and other water bodies;
to protect the life, health and property of the general public; to preserve
and enhance the suitability of waters for contact recreation and fish
habitat; to preserve and enhance the aesthetic quality of the waters; to
maintain and protect valuable groundwater quantities, locations and flow
patterns; to ensure the safety of city roads and rights-of-way; and to
decrease drainage-related damages to public and private property. (Ord. 2441
§ 1, 1997)
Section 13.36.020 Definitions.
Words and phrases used in this chapter have the meaning set forth in
this section:
"Authorized city official" means the Anacortes director of public works
or designee. May be cited in this chapter as only "official" for simplicity
of presentation.
"Best management practices (BMP)" means physical facilities, and/or
managerial practice, that when used singly or in combination prevent or
reduce pollution of water. BMPs include, but are not limited to:
infiltration, retention and/or detention facilities; biofiltration
facilities; open ditches with check dams; filter fabric-strips; oil/water
separators; constructed wetlands; erosion control; sedimentation controls,
and other water treatment/sediment and pollution abatement facilities.
"Biofiltration facility" means the simultaneous process of filtration,
infiltration, adsorption and biological uptake of pollutants in stormwater
that take place when runoff flows over and through vegetated treatment
facilities. The term includes vegetated open roadside drainage ditches.
"Computations" means calculations, including coefficients and other
pertinent data, made to determine the rates of flow for stormwater plans,
with units given in cubic feet per second.
"Critical area" means critical areas as defined in the city zoning
ordinance.
"Current conditions" means the state, status or condition of the subject
property at the time the application is made, which may include existing
buildings, impervious areas and topography as is.
"Design storm" refers to that rainfall event which is selected by the
city engineer for purposes of design, specifying both the return period in
years and the duration in hours.
"Detention facilities" means facilities designed to hold runoff while
gradually releasing it at a predetermined maximum rate.
"Developed conditions" means the state, status or condition of the
subject property at the time the proposed project has been completed, which
may include existing buildings, impervious areas and topography as is.
"Developer" means the individual(s) or corporation(s) or governmental
agency(ies) applying for the permits or approvals described in Section
13.36.030 of this chapter.
"Development" means any artificial change to property, including but not
limited to, building or other structures, mining, dredging, filling, all
land-disturbing activities, clearing, grading, landscaping, paving,
excavation or drilling operations.
"Developmental coverage" means all developed surface areas within the
subject property including but not limited to rooftops, driveways, carports,
accessory buildings, parking areas, and any other impervious surfaces.
During construction, "developmental coverage" includes the above in addition
to the full extent of any alteration of previously occurring soils, slope,
or vegetation due to grading, temporary storage, access areas, or any other
short-term causes.
"Drainage area" means the watershed contributing water runoff to and
including the subject property.
"Drainage facility" means structures or features, natural or artificial,
that convey, treat, and/or abate surface water runoff, including but not
limited to detention facilities, retention facilities and drainage
retention/abatement facilities.
"Drainage site" means a geographical area that serves a common or
combined use including but not limited to shopping malls and strips,
condominiums, apartment complexes, office parks and housing tracts. A site
may include one or more parcels and/or include one or more buildings. See
also Development.
"Drainage system" means the drainage system comprised of natural and
artificial systems that convey surface water within the city of Anacortes.
This system includes pipes, culverts, ditches, open channels, streams,
lakes, rivers, ponds, and detention and retention ponds, as well as other
types of conveyance facilities. Depending on its context, a "drainage
system" refers to either the public drainage system or a private drainage
system, or to both.
"Drainage treatment/abatement facilities" means any facilities installed
or constructed in conjunction with a drainage plan for the purpose of
treating urban runoff to improve water quality, excluding retention or
detention facilities.
"Ecology manual" means the Washington State Department of Ecology
(WSDOE) Stormwater Management Manual for the Puget Sound Basin.
"Illicit discharge" means all nonstormwater discharges to stormwater
drainage systems that cause or contribute to a violation of state water
quality, sediment quality, or groundwater quality standards, including but
not limited to sanitary sewer connections, industrial process water,
interior floor drains and gray water systems.
"Impervious areas" means that hard surface area which either prevents or
retards the entry of water into the soil mantle and/or causes water to run
off the surface in greater quantities or at an increased rate of flow from
that present under natural conditions. Impervious surfaces may include, but
are not limited to, rooftops, concrete or asphalt paving, graveled areas,
walkways, patios, driveways, parking lots or storage areas, and oiled,
macadam or other surfaces which similarly impede the natural infiltration or
runoff of surface water.
"King County manual" means King County Surface Water Design Manual.
"Land-disturbing activities" means any activity that disturbs or alters
land surface including clearing and grading.
"Large parcel stormwater plan (LPSP)" means a plan to implement BMPs to
control pollution generated during land-disturbing activity pursuant to
Section 13.36.110. Guidance for preparing an LPSP is contained in the
ecology manual or the King County manual.
"Natural location" of drainage systems means the location of those
channels, swales, and other natural conveyance systems as defined by the
first documented topographic contours existing for the subject property,
either from maps or photographs, or such other means as appropriate.
"New development" means the following activities: land-disturbing
activities; structural development, including construction, installation or
expansion of building or other structures; installation of impervious
surfaces; and subdivisions or short plats.
"Planned unit development" refers to residential developments which are
planned and/or developed in several stages but submitted together for
approvals, and which typically consist of clusters of structures
interspersed with areas of common open space.
"Pollutant" means any substance which, when added to water, would
contaminate or alter the chemical, physical or biological properties of any
waters of the city's drainage system or of the state. This includes a change
in temperature, taste, color, turbidity or odor of the waters, or such
discharge of any liquid, gaseous, solid, radioactive, or other substance
into any waters of the city's drainage system or of the state so as to
create, or is likely to create, a nuisance. It also includes any substance
which renders such waters harmful, detrimental or injurious to the public
health, safety, or welfare, or to domestic, commercial, industrial,
agricultural, recreational, or other legitimate beneficial uses, or to
livestock, wild animals, birds, fish or other aquatic life.
"Private drainage system" means drainage systems located on private
property and designed to discharge directly, as through pipes, channels,
etc., or indirectly as sheet flow, subsurface flow, etc., into the city's
drainage system.
"Public drainage system" means that portion of the drainage system of
the city located on public right-of-way or other property owned by the city,
and those portions of private drainage systems assumed by the city.
"Receiving bodies of water" means creeks, streams, lakes, and other
bodies of water into which waters from drainage systems are directed, either
naturally, in artificial ditches, or in closed conduit systems.
"Redevelopment" means on an already developed site, the creation and/or
addition of impervious surfaces, structural development including
construction, installation or expansion of a building or other structure,
and/or replacement of impervious surface that is not part of a routine
maintenance activity, and land-disturbing activities associated with
structural or impervious redevelopment.
"Retention facilities" means facilities designed to hold water for a
considerable length of time and then consume it by evaporation, plant
transpiration or infiltration into the soil.
"Small parcel stormwater plan (SPSP)" means a plan to implement BMPs to
control pollution generated during land clearing activity pursuant to
Section 13.36.100.
"Stormwater plan" means a plan approved by the city of Anacortes which
includes either a small parcel or large parcel stormwater plan and/or a
permanent stormwater quality control plan.
"Subject property" means the tract of land which is the subject of the
permit and/or approval action, as defined by the full legal description of
all parcels involved in the proposed development.
Terms of approval, judgment or direction. When the terms "approved,"
"subject to approval," "satisfactory," "equal to," "or equal," "proper," "as
directed," "where directed," "when directed," "determined by," etc., are
used, the approval, judgment or direction implied is understood to be a
function of city as represented by the authorized city official.
"Water quality control plan (WQCP)" means a plan which includes
permanent BMPs for the control of pollution from stormwater runoff after
construction and/or land-disturbing activity has been completed. (Ord. 2441
§ 2, 1997)
Section 13.36.030 Applicability.
A. All developers taking any of the following actions or applying for
any of the following permits and/or approvals may be required to submit for
approval a stormwater plan with their application and/or request:
1. Creation or alteration of new or additional impervious surfaces;
2. New development;
3. Redevelopment:
4. Building permit;
5. Subdivision approval;
6. Short subdivision approval;
7. Commercial, industrial or multifamily site plan approval;
8. Planned unit development;
9. Development within or adjacent to critical areas;
10. Rezones;
11. Conditional use permits;
12. Substantial development permit required under RCW 90.58
(Shoreline Management Act).
B. Commencement of construction work under any of the actions,
permits or applications set forth in subsection A of this section shall not
begin until the city approves a stormwater plan which may include one or
more of the following as required by this chapter:
1. Small parcel stormwater plan (SPSP), pursuant to Section
13.36.100;
2. Large parcel stormwater plan (LPSP), pursuant to Section
13.36.110;
3. Water quality control plan (WQCP), pursuant to Section 13.36.120.
C. Guidance on the approach to preparing a stormwater plan is
contained in both the Department of Ecology and King County manuals.
D. Whenever a minimum area or quantity requirement is set forth in
this chapter, such requirement shall be met if any activity or development
occurs that meets these requirements within a continuous eighteen-month
period. (Ord. 2441 § 3, 1997)
Section 13.36.040 Exemptions.
A. Throughout the ordinance codified in this chapter various
requirements are conditioned upon the authorized city official's authority
to waive a requirement. This grant of authority does not mean that the
official may arbitrarily waive standards and requirements of this chapter.
It means that the standards and requirements in this chapter will apply
except in cases when the official determines, after review of a
properly-filed request for exemption, that the proposed activity will not
cause any of the following conditions:
1. Adversely impact the water quality conditions of any affected
receiving bodies of water,
2. Alter drainage patterns, increase the runoff volume, increase the
peak discharge, or cause any other adverse effects in the drainage area,
3. Alter the subsurface drainage patterns, flow rates and discharge
points, or result in any significant adverse effects to property or
residents,
4. Cause runoff exceeding the available capacity of the existing
drainage system,
5. Raise the existing high water level or reduce the flood-carrying
capacity of any water course, and
6. Increase, beyond the subject property boundaries, the velocities
downstream, nor raise the backwater upstream;
B. Development undertaken by the Washington State Department of
Transportation in state highway rights-of-way which is regulated and meets
the requirements of Chapter 173-270 WAC, the Puget Sound Highway Runoff
Program, is exempted from the requirement of this chapter;
C. Commercial agriculture, including only those activities conducted
on lands defined in RCW 84.34.020(2), and production of crops or livestock
for wholesale trade;
D. Forest practices regulated under Title 222 Washington
Administrative Code, except for Class IV general forest practices, as
defined in WAC 222-16-050, that are conversions from timber land to other
uses;
E. Requests for exemption shall be filed in writing with the
official, and shall adequately detail the basis for granting an exemption;
F. The official shall notify the city council of the intent to issue
an exemption to this chapter as allowed by this section;
G. The decision of the official, as to an exemption or denial
thereof, may be appealed to the city council by filing written notice of
appeal with the city clerk within ten days of service of the director's
decision. The cost of the appeal shall be one hundred fifty dollars. (Ord.
2441 § 4, 1997)
Section 13.36.050 Best management practices (BMPs).
BMPs shall be used to control and treat the quantity and quality of
stormwater before it leaves the site. BMPs shall be used to comply with the
standards in this chapter. Guidance for the approach to design,
implementation and maintenance of BMPs are provided in the latest Department
of Ecology and King County manuals in existence at the time of adoption of
the ordinance codified in this chapter.
The type, location and quantity of BMPs employed on a project shall be
approved by the official. BMPs may be modified and/or increased during the
construction phase should the official determine the proposed BMPs to be
inadequate to achieve the result desired.
Wet ponds will not be allowed, unless approved by the official. (Ord.
2441 § 5, 1997)
Section 13.36.060 Illicit discharges.
A. Discharges Prohibited to Public Drainage Systems. All illicit
discharges, as defined in Subsection B below, made either directly or
indirectly to a public drainage system, are prohibited and constitute a
violation of this chapter.
Stormwater shall not be allowed to enter the sanitary sewer system,
through either direct connection or surface waters entering through manhole
lids, etc.
B. Illicit Discharges Defined. Except as provided in subsection C
below, all discharges which are not composed entirely of stormwater are
illicit discharges.
The following is a partial list, provided for informational purposes
only, of common substances which are illicit discharges when allowed to
enter a public drainage system:
Solid waste; human and animal waste; antifreeze, oil, gasoline, grease,
and all other automotive and petroleum products; flammable or explosive
materials, metals in excess of naturally occurring amounts, whether in
liquid or solid form; chemicals not normally found in uncontaminated water;
solvents and degreasers; paint products; drain cleaners; commercial and
household cleaning materials; pesticides; herbicides; fertilizers; acids;
alkalis; ink; steam-cleaning waste; laundry waste; soap; detergent; ammonia;
chlorine; chlorinated swimming pool or hot tub water; domestic or sanitary
sewage; animal carcasses; food and food waste; yard waste; dirt; sand;
cement; plaster; dry-wall compound; and gravel.
C. Permissible Discharges. Discharges from the sources listed below
shall only be illicit discharges if determined that the type of discharge,
whether singly or in combination with others, is causing or contributing to
a water quality violation or is causing or contributing to a water quality
problem, such as those which contain more contamination than typical
discharges in the city, or which contain a type of contamination that is
more toxic or is otherwise a more serious problem than typical discharges in
the city:
Potable water sources; washing of potable water storage reservoirs;
flushing of potable water lines; natural uncontaminated surface water;
natural uncontaminated groundwater; air conditioning condensation; natural
springs; uncontaminated water from crawl space pumps; uncontaminated runoff
from lawn watering; uncontaminated irrigation runoff; flows from riparian
habitats and wetlands; and discharges from footing drains and other approved
subsurface drains or, where approval is not required, installed in
compliance with this chapter and rules promulgated pursuant to this chapter.
D. Exemption. Discharges resulting from public firefighting
activities, but not from activities not related to firefighting, such as the
maintenance or cleaning of firefighting equipment, are exempt from
regulation under this section.
E. Testing for Illicit Discharges. When the authorized city official
has reason to believe that any discharge is an illicit discharge, the
official may arrange for a responsible party to sample and analyze the
discharge at the city's expense, and to provide an analysis of the data to
the city. If it is found that the discharge was an illicit discharge, the
city will recover the related investigation costs from the responsible party
in an enforcement proceeding. When a discharge is judged likely to contain
illicit discharges on a recurring basis, city may conduct ongoing monitoring
at the responsible party's expense or may require the responsible party to
conduct such monitoring. (Ord. 2441 § 6, 1997)
Section 13.36.070 General design and construction standards.
Unless otherwise provided, it shall be the developer's and property
owner's responsibility to design, construct and maintain a system which
complies with these standards and minimum requirements.
A. Surface water entering the subject property shall be received at
the naturally occurring locations, and surface water exiting the subject
property shall be discharged with adequate energy dissipaters within the
subject property to minimize downstream damage into the naturally occurring
drainage basins to the maximum extent possible, as determined by the
official.
B. Where open channel construction is used to handle drainage within
the subject property, the following standards shall apply:
1. In open channel work, the water surface elevation from the ten-
and one hundred-year design storms shall be indicated at upstream and
downstream points which cross the subject property boundaries, at sudden
grade changes, and/or other locations as deemed necessary on the plan and
profile drawings. The configuration of the finished grades constituting the
banks of the open channel, typical cross-sections of channel geometry, and
hydraulic gradelines as appropriate shall also be shown on the drawings.
2. The proposed cross-section of the channel will be shown with
stable side slopes at minimum horizontal to vertical ratio of 3:1 or flatter
or as approved.
C. When a closed system is used to handle drainage within the subject
property, the system shall be a minimum of ten feet from all structures.
Closed drainage systems or culverts on an existing, defined watercourse,
stream or creek shall be designed to convey flows from a one hundred-year
recurrence storm event. All other closed drainage systems shall be designed
to convey flows from a twenty-five-year recurrence storm event.
D. All drainage easements granted to the city within the subject
property shall be at least twenty feet in width for operation and
maintenance of open channel or closed system installation.
E. Where drainage facilities discharge to natural drainage ways
and/or watercourses, approved energy dissipation facilities shall be
provided to minimize erosion and deterioration of the stream bed or banks.
Materials such as broken concrete slabs, pipe, tires, scrap metal or debris
are prohibited for use as energy dissipaters.
F. All nonmetallic underground drainage facilities installed during
construction shall have tracer tape placed a minimum depth of one foot above
the facility.
G. In addition to any other applicable requirements, all drainage
systems directing water from single-family residential rooftops and footing
drains shall be either (i) tight-lined to a storm drainage system, (2)
discharged to a dry well, (3) infiltrated through a French drain system, (4)
dispersed to vegetated ground using a splash block, or (5) other similar
handling as approved.
H. Surrounding properties shall be protected from stormwater runoff
from the development. This shall be accomplished be constructing private
drain lines on the perimeter of the development and discharging the storm
runoff into a public storm sewer system. Open space tracts and buffers shall
not be used for this purpose, unless otherwise approved. Private drain lines
shall be contained in private drainage easements with appropriate statements
placed on approving documents.
I. Drainage conveyance shall be provided to all impervious areas of
the development. Each lot or other developed area shall be provided with
direct connection to the main public stormwater conveyance system; sidewalk
drains will only be allowed with approval of the official. Adequate
provisions, to the satisfaction of the official, must be provided for
directing stormwater runoff away from all neighboring lots. This may be
accomplished by providing private drainage easements on common lot lines
and/or construction of drainage swales, curtain drains, or perforated pipe
and connecting to the public storm conveyance system.
J. Verification shall be provided to the city engineer that the
as-built detention/retention facility is in compliance with the project
requirements. This shall be certified by the design engineer.
K. All site-generated storm runoff shall be directly conveyed to a
public storm conveyance system, unless otherwise approved by the official.
Easements and/or hold-harmless agreements shall be obtained from affected
property owners to allow passage of all site-generated storm runoff that is
not directly conveyed to a contiguous public storm conveyance system.
L. The finished surface of the pond bottom and sides, both internal
and external, shall be graded to a smooth, mowable grade, free of all rocks,
wood or other material greater than one inch in any direction. Transitions
between both adjoining sideslopes and the pond bottom shall not meet at a
hinge point but employ a curve with a radius not less than twenty-five feet.
Immediately prior to final acceptance of improvements and when the pond
is no longer being used for sedimentation control, the pond bottom shall be
lined with fresh, living and viable grass sod to an elevation one foot above
the bottom, unless otherwise approved by the official. The sides of the pond
shall be dressed with topsoil and raked, then seeded with a quick
germinating grass seed, after March 15th and before September 15th, at an
application rate approved by the official. Other methods of soil
stabilization shall be required from September 16th to March 14th, as
approved by the official.
M. Retention/detention pond interior sideslopes shall not be steeper
than 5H:IV. The official may allow steeper slopes if, in the official's
opinion, public safety and provisions for facility maintenance are not
compromised.
N. Maintenance of all drainage facilities constructed or modified by
a proposed project is the responsibility of the property owner, except the
city, at its discretion, may assume maintenance of drainage facilities
constructed for formal plat subdivisions, planned unit developments, and
conditional use permits. (Ord. 2441 § 7, 1997)
Section 13.36.080 General water quantity standards.
A. All retention/detention facilities shall be analyzed using the
Santa Barbara Urban Hydrograph method as outlined in the DOE manual, and in
accordance with design release standards contained within this chapter.
Rainfall data applicable to the city shall be used as the basis for analyses
and designs hereunder.
B. Open retention/detention ponds and infiltration facilities shall
not be located in dedicated public road right-of-way areas unless
specifically approved by the Anacortes city council.
C. Emergency overflow provisions shall be installed in such a manner
as to direct flow away from all structures and prevent failure of those
structures from stormwaters. Retention/detention and infiltration facility
design must take into account and provide mitigation for overflows which may
result from:
1. Higher-intensity or longer-duration storms than the one
hundred-year design storm;
2. Plugged orifices;
3. Inadequate storage due to sediment buildup;
4. Debris blockage; or
5. Other reasons causing system failure.
D. No more that twenty-five percent of public parking shown on the
plan shall be used for stormwater retention/detention, and the maximum depth
of the retention/detention facilities cannot exceed six inches in public
parking areas. No retention/detention shall occur on parking areas
designated for multiple-residential development. (Ord. 2441 § 8, 1997)
Section 13.36.090 General water quality standards.
A. Approved spill prevention facilities such as oil/water separators
and containment berms shall be incorporated into all drainage plans where
applicable.
B. All storm and surface water discharges shall be treated using
approved best management practices.
C. Treatment BMPs shall be sized to capture and treat the water
quality design storm, defined as the six-month, 24-hour return period storm.
(Ord. 2441 § 9, 1997)
Section 13.36.100 Small parcel requirements.
A. Development Subject to Small Parcel Requirements. Each of the
following new types of developments shall control erosion and sediment
transport during construction, and permanently stabilize soil exposed during
construction in accordance with the requirements of this section:
1. Individual, detached, single-family residences and duplexes;
2. Creation or addition of more than one thousand and less than five
thousand square feet of impervious area;
3. Grading, clearing or land-disturbing activities of more than one
thousand square feet and less than one acre.
B. Plans for such development shall include a site plan and a small
parcel stormwater plan (SPSP). Based upon the review of the small parcel
stormwater plan, a determination will be made as to whether or not further
drainage plans or information are needed.
C. Site Plan. The site plan shall indicate the character of the
existing site, topography, natural drainage features on or adjacent to the
site, the location and dimensions of all existing and proposed impervious
surfaces, flow arrows indicating the direction of stormwater flows on-site,
and any off-site flows entering the site, the proposed method of utilizing
the existing drainage system, the temporary erosion/sedimentation control
plan and the permanent soil stabilization measures to be employed.
D. Services of Professional Engineer. If the parcel contains or is
adjacent to either a floodplain, a stream, a lake, a closed depression, a
wetland, or an erosion or landslide hazard area (as indicated by land slopes
and general soil types) a registered professional civil engineer shall
prepare the plan.
E. Compliance. Compliance shall be demonstrated through the
implementation of an approved small parcel stormwater plan.
F. Small Parcel Stormwater Plan (SPSP). In addition to meeting the
requirements of Section 13.36.070, General design and construction
standards, Section 13.36.080, General water quantity standards, and Section
13.36.090, General water quality standards, all plans subject to SPSP shall
meet the following requirements:
1. SPSP No. 1 -- Construction Access Route.
a. Construction vehicle access shall be limited to one route, unless
approved by the official.
b. A gravel construction road shall be installed which will remove as
much mud and dirt from the vehicles as possible prior to entering the public
roadway. The effectiveness and efficiency of the removal shall be to the
satisfaction of the official.
c. If conditions are such that an insufficient amount of material is
removed from the tires by contact with the aggregate, the tires shall be
washed prior to entering the public right-of-way. The water from this
process shall be directed to a sedimentation pond or other appropriate
sediment-trapping BMP for treatment prior to release to the public
stormwater system.
d. The entrance shall be maintained in a condition that shall prevent
the tracking or flow of mud onto the public right-of-way. Periodic
maintenance of the entrance, including the removal and replacement of
aggregate, and cleaning and/or repair of sediment-trapping devices shall be
performed as conditions dictate or as directed by the official.
e. Sediment tracked onto the public roadways shall be cleaned on at
least a daily basis.
2. SPSP No. 2 -- Stabilization of Denuded Areas. All exposed soils
shall be prevented from moving off-site or into natural or artificial
drainage systems through suitable application of BMPs, including but not
limited to sod or other vegetation, plastic covering, mulching, or
application of ground base on areas to be paved.
3. SPSP No. 3 -- Protection of Adjacent Properties. Adjacent
properties shall be protected from sediment deposition by appropriate use of
vegetative buffer strips, sediment barriers or filters, dikes, berms, or
mulching, or by a combination of these measures and other appropriate BMPs.
a. Surrounding properties shall be protected from stormwater runoff
from the development. This shall be accomplished by constructing private
drain lines on the perimeter of the development and discharging the storm
runoff into a public storm sewer system. Open space tracts and buffers shall
not be used for this purpose, unless otherwise approved. Private drain lines
shall be contained in private drainage easements with appropriate statements
placed on approving documents.
b. Drainage conveyance shall be provided to all impervious areas of
the development. Each lot or other developed area shall be provided with
direct connection to the main public stormwater conveyance system; sidewalk
drains will only be allowed with approval of the official. Adequate
provisions, to the satisfaction of the official, must be provided for
directing stormwater runoff away from all neighboring lots. This may be
accomplished by providing private drainage easements on common lot lines
and/or construction of drainage swales, curtain drains or perforated pipe
and connecting to the public storm conveyance system.
c. Verification shall be provided to the city engineer that the
as-built detention/retention facility is in compliance with the project
requirements.
d. All site-generated storm runoff shall be directly conveyed to a
public storm conveyance system, unless otherwise approved by the official.
Easements and/or hold-harmless agreements shall be obtained from affected
property owners to allow passage of all site-generated storm runoff that is
not directly conveyed to a contiguous public storm conveyance system.
e. Adjacent properties shall be protected from sediment deposition by
appropriate BMPs including, but not limited to, vegetative buffer strips,
sediment barriers or filters, dikes, berms, or mulching, or by a combination
of these and other appropriate measures.
4. SPSP No. 4 -- Maintenance. All erosion and sediment control BMPs
shall be inspected and maintained regularly by the developer to ensure
continued performance of their intended function.
5. SPSP No. 5 -- Other BMPs. Other appropriate BMPs to mitigate the
effects of increased runoff or inadequacy of already installed BMPs shall be
applied as required or ordered by the official.
G. Financial Liability. Performance bonding, or other appropriate
instruments, may be required for all projects to ensure compliance with the
approved small parcel stormwater plan. (Ord. 2441 § 10, 1997)
Section 13.36.110 Large parcel requirements.
A. Development Subject to Large Parcel Requirements. For the
following new development and redevelopment involving actions, permits and
approvals that satisfy the following thresholds, the applicant shall comply
with the requirements described in this section:
1. All new development that includes the creation or addition of five
thousand square feet or more of impervious surface area, and/or
land-disturbing activity of one acre or greater, shall comply with the
requirements of this section including large parcel stormwater plan
requirements (LPSPR) 1 through 11 and the requirements of Section 13.36.070,
General design and construction standards, Section 13.36.080, General water
quantity standards, and Section 13.36.090, General water quality standards.
Compliance shall be demonstrated through the implementation of an approved
large parcel stormwater plan (LPSP) and a water quality control plan (WQCP).
2. All new development that includes: (a) the creation or addition of
five thousand square feet or more of new impervious surface area, and (b)
land-disturbing activity of less than one acre, shall comply with large
parcel stormwater plan requirements (LPSP), No. 1, subparagraphs a, c, d, j
and n, Nos. 2 through 11 and the requirements of Section 13.36.070, General
design and construction standards, Section 13.36.080, General water quantity
standards, and Section 13.36.090, General water quality standards.
Compliance shall be demonstrated through the implementation of an approved
large parcel stormwater plan (LPSP) and a water quality control plan (WQCP).
B. Redevelopment of Developed Sites.
1. Redevelopment Requiring LPSP for Redeveloped Area Only. Where
redevelopment of area greater than or equal to five thousand square feet of
impervious surface is proposed, the large parcel stormwater plan (LPSP) and
the water quality control plan (WQCP) shall be required for that portion of
the site that is being redeveloped. Source control BMPs, as described in the
Department of Ecology or King County manuals, shall be applied to the entire
site, including adjoining parcels if they are part of the project.
2. When one or more of the following conditions apply, and unless
otherwise approved, the large parcel stormwater plan and a water quality
control plan shall be required for the entire site. A schedule shall also be
completed showing how these requirements will be implemented for the entire
site, including adjoining parcels if they are part of the project.
a. Existing or current sites greater than or equal to one acre in
size with fifty percent or more impervious surface;
b. Sites that discharge to a receiving water that has a documented
water quality problem. A documented water quality problem includes, but is
not limited to water bodies:
i. Listed in reports required under Section 305(b) of the Clean Water
Act, and designated as not supporting beneficial uses,
ii. Listed under Section 304(1)(1)(A)(i), 304(1)(l)(A)(ii), or
304(1)(1)(B) of the Clean Water Act as not expected to meet water quality
standards or water quality goals,
iii. Listed in Washington State's Nonpoint Source Assessment required
under Section 319(a) of the Clean Water Act that, without additional action
to control nonpoint sources of pollution cannot reasonably be expected to
attain or maintain water quality standards.
3. Lien. In the event of the owner's failure to comply with the
provisions in the redevelopment schedule for implementing minimum
requirements over the entire site, work may be done by and under the
authority of the city, at the expense of the owner, and the expense to the
owner shall become a lien on the owner's property, following assessment as
provided by law, and may be collected by due process of law.
C. Additional Stormwater Control Measures. For sites where the need
for additional stormwater control measures have been identified through a
basin plan, the watershed ranking process under Chapter 400-12 WAC, or
through Growth Management Act planning, additional stormwater control
measures shall be required, unless a variance is granted.
D. Large Parcel Stormwater Plan Requirements (LPSPR).
1. LPSPR No. 1 -- Erosion and Sediment Control Plan. A large parcel
stormwater plan shall be prepared showing how the following requirements
will be accomplished:
a. Soil Stabilization and Sediment Trapping. All exposed and unworked
soils shall be stabilized according to a timetable established by the
director using suitable application of BMPs. Prior to leaving the site,
stormwater runoff shall pass through a sediment point or sediment trap, or
other appropriate BMPs.
b. Delineate Clearing and Easement Limits. Clearing limits,
easements, setbacks, sensitive/critical areas and their buffers, trees, and
drainage courses shall be delineated, by the project surveyor, with orange
plastic construction fencing prior to the commencement of land clearing
activities.
c. Protection of Adjacent Properties. Properties adjacent to the
project site shall be protected from sediment deposition.
d. Timing and Stabilization of Sediment Trapping Measures. Sediment
ponds and traps, perimeter dikes, sediment barriers, and other BMPs intended
to trap sediment on-site shall be constructed as a first step in grading.
These BMPs shall be functional before land-disturbing activities take place.
Earthen structures such as dams, dikes and diversions shall be seeded and
mulched.
e. Cut and Fill Slopes. Cut and fill slopes shall be designed and
constructed in a manner that will minimize erosion. In addition, slopes
shall be stabilized in accordance with erosion and sediment control
requirements in this section.
f. Controlling Off-Site Erosion. Properties and waterways downstream
from development sites shall be protected from erosion due to increases in
the volume, velocity and peak flow rate of stormwater runoff from the
project site.
g. Stabilization of Temporary Conveyance Systems. All temporary
on-site conveyance channels shall be designed, constructed, and stabilized
to prevent erosion from the expected peak velocity of flow from a two-year,
twenty-four-hour frequency storm for the developed condition. Stabilization
adequate to prevent erosion of outlets, adjacent stream banks, slopes and
downstream reaches shall be provided at the outlets of conveyance systems.
h. Storm Drain Inlet Protection. All storm drain inlets made operable
during construction shall be protected so that stormwater runoff shall not
enter the conveyance system without first being filtered or otherwise
treated to remove sediment.
i. Underground Utility Construction. The construction of underground
utilities shall be subject to the following:
i. Where feasible, no more than two hundred fifty feet of trench
shall be opened at one time.
ii. Where consistent with safety and space considerations, excavated
material shall be placed on the uphill side of trenches.
iii. Trench and foundation dewatering devices shall discharge into a
sediment trap or sediment pond, where practicable.
j. Construction Access Routes. Wherever construction vehicle access
routes intersect paved roads, provisions must be made to minimize the
transport of sediment (mud and dirt) onto the paved road. If sediment is
transported onto a road surface, the roads shall be cleaned thoroughly at
the end of each day. Sediment shall be removed from roads by shoveling or
sweeping and be transported to a controlled sediment disposal area. Street
washing shall be allowed only after sediment is removed in this manner.
k. Removal of Temporary BMPs. All temporary erosion and sediment
control BMPs shall be removed within thirty days after final site
stabilization is achieved or after the temporary BMPs are no longer needed.
Trapped sediment shall be removed or stabilized on site. Disturbed soil
areas resulting from removal shall be permanently stabilized.
l. Dewatering Construction Sites. Dewatering devices shall discharge
into a sediment trap or sediment ponds.
m. Control of Pollutants. All pollutants other than sediment that
occur on site during construction shall be handled and disposed of in a
manner that does not cause contamination of stormwater or surface waters.
n. Maintenance. All temporary and permanent erosion and sediment
control BMPs shall be maintained and repaired as needed to assure continued
performance of their intended function. All maintenance and repair shall be
conducted in accordance with the Department of Ecology Manual.
o. Financial Liability. Performance bonding, or other appropriate
instruments, may be required for all projects to ensure compliance with the
approved erosion and sediment control plan.
2. LPSPR No. 2 -- Preservation of Natural Drainage Systems. Unless
otherwise directed, natural drainage patterns shall be maintained, and
discharged from the site into the naturally occurring drainage basins at the
natural location, to the maximum extent practicable, as determined by the
official.
3. LPSPR No. 3 -- Source Control of Pollution. Source control BMPs
shall be applied to all projects to the maximum extent practicable. Source
control BMPs shall be selected, designed, and maintained according to the
Department of Ecology and King County manuals.
4. LPSPR No. 4 -- Runoff Treatment BMPs.
a. All projects shall provide treatment of stormwater. Treatment BMPs
shall be sized to capture and treat the water quality design storm, defined
as the six-month, twenty-four-hour return-period storm. The first priority
for treatment shall be to infiltrate as much as possible of the water
quality design storm, only if site conditions are appropriate and
groundwater quality will not be impaired. Direct discharge of untreated
stormwater to groundwater is prohibited except for roof drains. All
treatment BMPs shall be selected, designed and maintained according to the
Department of Ecology Manual.
b. Stormwater treatment BMPs shall not be built within critical area
vegetated buffers, except for necessary conveyance systems as approved.
5. LPSPR No. 5 -- Detention.
The requirement below must be met in addition to meeting the requirement
of LPSPR No. 4.
a. Stormwater discharges leaving a site shall be detained by
designing a pond that will limit the peak rate of runoff from individual
development sites for the two-year, twenty-four-hour design storm to fifty
percent of the current condition two-year, twenty-four-hour design storm
runoff rate while maintaining the current condition peak runoff rate for the
ten-year, twenty-four-hour and one hundred-year, twenty-four-hour design
storms.
b. After sizing the pond and the outlet structure according to the
criteria listed above, a thirty percent increase in storage volume must be
added at each foot of depth. As the first priority, stream bank erosion
control BMPs shall utilize infiltration to the fullest extent practicable,
only if site conditions are appropriate and groundwater quality is
protected. These control BMPs shall be selected, designed and maintained in
accordance with the Department of Ecology Manual.
c. Stormwater treatment BMPs shall not be built within vegetated
buffers, except for necessary conveyance systems as approved.
d. An adopted city stormwater quality management plan may establish
detention requirements that supersede the requirements contained within this
section.
6. LPSPR No. 6 -- Wetlands.
Where stormwater discharges to a wetland, in addition to the
requirements of LPSPR No. 4, the following apply:
a. Prior to discharge to wetlands, stormwater will be treated with
all reasonable best management practices for water quality protection.
b. Discharges to wetlands shall maintain water level fluctuations
similar to those which would be present under natural conditions.
c. The project applicant shall obtain all necessary state and federal
wetlands permits prior to commencing any work on the site.
d. Stormwater treatment BMPs shall not be built within natural
vegetated critical area buffers, except for necessary conveyance systems as
approved.
7. LPSPR No. 7 -- Water Quality Sensitive Areas. Where the official
determines that the minimum requirements do not provide adequate protection
of water quality sensitive areas, either on site or within the drainage
basin, more stringent controls shall be required to protect water quality.
Stormwater treatment BMPs shall not be built within natural vegetated
critical area buffers except for necessary conveyance systems as approved.
8. LPSPR No. 8 -- Off-Site Analysis and Mitigation. All projects
shall conduct a written analysis of off-site water quality and quantity
impacts resulting from the project and shall mitigate these impacts. The
analysis shall extend a minimum of one-fourth-mile downstream from the
project. The existing or potential impacts to be evaluated and mitigated
shall include, at a minimum, but not be limited to:
a. Excessive sedimentation;
b. Stream bank erosion;
c. Discharges to groundwater contributing or recharge zones;
d. Violations of water quality standards;
e. Spills and discharges of priority pollutants;
f. Inadequate or nonexistent stormwater conveyance system capacities;
g. Excessive stormwater velocities;
h. Existing problems.
9. LPSPR No. 9 -- City Basin Planning. Adopted city plans with
requirements for individual watershed-basins may be used to modify any or
all of these large parcel stormwater plan requirements, provided that the
level of protection for surface or groundwater achieved by the plans will
equal or exceed that which would be achieved by the LPSP requirements in the
absence of these plans. Basin plans shall evaluate and include, as
necessary, retrofitting of BMPs for existing development and/or
redevelopment in order to achieve watershed-wide pollutant reduction goals.
Standards developed from basin plans shall not modify any of the above
requirements until the basin plan is formally adopted and fully implemented
by the city.
10. LPSPR No. 10 -- Operation and Maintenance. An operation and
maintenance schedule shall be provided for all proposed stormwater
facilities and BMPs, and the party (or parties) responsible for maintenance
and operation shall be identified.
11. LPSPR No. 11 -- Financial Liability. Performance bonding and/or
other appropriate financial instruments shall be required for all projects
to ensure compliance with these standards.
E. Engineer Required. The large parcel stormwater plan shall be
prepared by a professional civil engineer registered in the state. (Ord.
2441 § 11, 1997)
Section 13.36.120 Water quality control plan (WQCP).
The detailed form and contents of the WQCP shall be as follows:
A. The WQCP shall be prepared and certified by a professional civil
engineer registered in the state.
B. The contents of a WQCP shall include the following:
1. Project Description.
a. A legal description of the property,
b. The name(s), address(es) and telephone number(s) of the owner(s)
and person(s) ordering the work to be performed,
c. To the extent necessary to adequately evaluate the accuracy of
computations, the project description will include:
i. The location of any existing or proposed buildings, structures and
utilities on the property where the work is to be performed, and
ii. The location of any existing building or structure on the
adjacent property which is within fifteen feet of where the work is to be
performed,
d. Elevations, dimensions, location, extent, and the slopes of all
work proposed to be done, shown on a contour map. Such contour map shall
show existing and proposed contours. A minimum of a two-foot contour
interval or otherwise as approved shall be used to adequately show drainage
courses through the property and shall relate to the grade changes on the
property. The datum used to depict information related to elevations will be
as approved,
e. The soils types and existing and proposed vegetative cover,
including trees, shrubs and grasses, shall be depicted on a map of the site,
f. Location of existing and proposed drainage features which
transport water onto, across, or from the site including natural creeks,
swales, artificial channels, drains or culverts. Also locations of springs,
or other subsurface water outlets as well as ponds, lakes, swamps, wetlands,
wet ponds, critical areas or potholes shall be shown on the contour map;
2. Background Computations for Sizing Drainage Facilities.
a. Topographical map of approved scale and contour interval showing:
i. Existing and proposed drainage basins,
ii. Acreage of existing and proposed pervious and impervious areas,
and
iii. Slopes/grades and lengths of the existing and proposed
time-of-concentration (Tc) lines,
b. Indication of the peak discharge and volume of surface water,
assuming current conditions, entering and leaving the subject property due
to the design storm,
c. Indication of the peak discharge and volume of runoff which will
be generated due to the design storms, assuming developed conditions, within
the subject property,
d. Determination of the peak discharge and volume of water that will
be generated by the design storm, assuming undeveloped and developed
conditions, at critical points on the subject property and at all naturally
occurring discharge points off the property;
3. Proposed measures for handling the computed runoff in accordance
with the requirements in this chapter;
4. Proposed measures for controlling runoff and erosion/sedimentation
during clearing, grading and construction; and proposed staging and schedule
of all building, clearing and grading activities in accordance with this
chapter and the Department of Ecology and King County manuals;
5. Proposed schedule for maintenance of all applicable storm
drainage-related facilities. The maintenance schedule shall extend for the
life of the facility;
6. Detailed information regarding surface and pertinent subsurface
water flows entering, flowing within, and leaving the subject site, both
during and after construction;
7. Compliance with the provisions for large parcel stormwater plan
requirements Nos. 2 through 11;
8. Provisions set forth in Section 13.36.070, General design and
construction standards, Section 13.36.080, General water quantity standards,
and Section 13.36.090, General water quality standards. (Ord. 2441 § 12,
1997)
Section 13.36.130 Additional information.
The requirements of this chapter for information submittals including
design criteria, calculations, drawings, etc., may be modified at the
discretion of the authorized city official when such additional information
is deemed necessary for proper review. (Ord. 2441 § 13, 1997)
Section 13.36.140 Review and approval.
A. All storm drainage plans prepared in connection with any of the
permits and/or approvals listed in Section 13.36.030 shall be submitted for
review by and approval of the authorized city official.
B. The official may approve, conditionally approve, or deny an
application for activities regulated by this chapter. (Ord. 2441 § 14, 1997)
Section 13.36.150 Inspection--Construction.
A. All activities regulated by this chapter shall be inspected.
Projects will be inspected at various stages of the work to determine that
adequate control is being exercised.
B. Stages of work requiring inspection include, but are not limited
to: preconstruction; installation of BMPs; land-disturbing activities;
installation of utilities, landscaping, retaining walls; and completion of
project.
C. At the time of approval of the drainage plan for the subject
property, a schedule for inspection to ensure proper review of construction
and facilities will be established by the official. (Ord. 2441 § 15, 1997)
Section 13.36.160 Modification of facilities during
construction.
The city may require that the construction of drainage facilities and
associated project designs be modified or redesigned if conditions occur or
are discovered which were not considered or known at the time the permit or
approval was issued, such as uncovering unexpected soil and/or water
conditions, weather-generated problems, or undue materials shortages. Any
such modifications made during the construction of drainage control
facilities shall be recorded on the final approved drainage plan, a revised
copy of which shall be provided to the city. (Ord. 2441 § 16, 1997)
Section 13.36.170 Fees.
Fees shall be charged for review of small parcel stormwater plans, large
parcel stormwater plans and water quality control plans. Review fees shall
be paid in advance of such reviews. The schedule of fees is set forth in the
city's fee structure ordinance. (Ord. 2441 § 17, 1997)
Section 13.36.180 Prohibited acts.
It shall be prohibited and in violation of this chapter for any person
or entity to:
A. Cause or permit litter, trash, rubbish or debris to enter the
public roadways or drainage system or any private drainage system which may
directly or indirectly discharge to the city's drainage system.
B. Cause or permit pollutants to enter any private drainage system or
the public drainage system, including but not limited to oils and petroleum
products, paints and paint thinners, pesticides, fertilizers, soaps,
detergents, washing wastes, and any pollutants found on the following lists,
as now or hereafter amended, adopted in this section as part of this chapter
by reference:
1. Discarded Chemicals List of WAC 173-303-9903,
2. Toxic Dangerous Waste List of WAC 173-303-101,
3. Dangerous Waste Sources List of WAC 173-303-9904,
4. Dangerous Waste Constituents List of WAC 173-303-9905,
5. Dangerous Waste Mixtures List of WAC 173-303-084,
6. Persistent Dangerous Waste List of WAC 173-303-102;
C. Cause any damage to any drainage facilities of any private
drainage system or the public drainage system;
D. Cause or permit horses, cattle, or other domestic animals to enter
any watercourses or wetlands that are part of the drainage system of the
city. Stormwater for stables, pastures, and other animal enclosures shall be
diverted so as to prevent polluted drainage waters from entering the
drainage system of the city;
E. Cause or permit grading, clearing, filling, or other land surface
changes to take place in such a way as to allow drainage from the property
to carry any suspended or dissolved matter into the drainage system of the
city;
F. Cause or permit any work that would result in the transmission of
silt, pollution materials, or other foreign substances from one part of the
drainage system to another;
G. Discharge any waters or in any way cause the temperature of the
water discharged from the property to exceed by more than five degrees
Fahrenheit the temperature of the nearest receiving waters;
H. Introduce into the drainage system any liquid or solid foreign
substances of biodegradable or other nature which shall cause the water
quality to degrade from Class A water quality standards of the state (WAC
173-201);
I. Unless approved, no obstructions of any kind shall be placed or
allowed which would prohibit the free passage of fish. (Ord. 2441 § 18,
1997)
Section 13.36.190 General maintenance requirements.
A. It shall be the duty of the property owner to maintain, repair and
restore, at the owner's expense, all private stormwater and drainage systems
located on the owner's property, in accordance with the city stormwater
maintenance ordinance in accordance with a maintenance schedule adopted
during the plan review process for the project.
B. No person shall cause or permit any drainage system located on the
owner's property to be obstructed, filled, graded or used for disposal of
debris. (Ord. 2441 § 19, 1997)
Section 13.36.200 Monitoring facilities.
A. As provided for in Section 13.36.060E, monitoring for
likely-recurring illicit discharges may be deemed necessary at a particular
site. When such monitoring is required, the owner shall furnish drainage
facilities which provide for adequate access, inspection, sampling and flow
measurement of such discharges into the city's stormdrain system. The design
shall be approved and shall be site specific. The facility shall be located
on the owner's premises except where impracticable and as otherwise
approved.
B. The monitoring facilities and sampling or measuring equipment
shall be furnished and maintained in safe and proper operating condition at
all times and at the owner's expense.
C. The monitoring facilities shall be built and maintained in
accordance with applicable construction standards, and specifications, and
shall be completed within one hundred eighty days of notice to do so.
D. Stormwater sampling requirements shall be in accordance with
procedures established by the EPA as contained in 40 CFR part 136 (the
federal Clean Water Act) as now existing or hereafter amended. Results of
sampling and analysis shall be reported to the city. (Ord. 2441 § 20, 1997)
Section 13.36.210 Waiver of requirements of this chapter.
A. Waiver of the requirements of this chapter may be granted for good
cause, considering the following criteria:
1. Sufficient capacity of downstream facilities under design
conditions;
2. Maintenance of the integrity of the receiving waters;
3. Possibility of adverse effects of retention/detention;
4. Utility of regional retention/detention facilities;
5. Capability of maintenance of the system;
6. Structural integrity of abutting foundations and structures;
7. Requirements of the city surface water quality management plan;
8. That the health, safety and welfare of the city is not adversely
affected;
9. The exception provides equivalent environmental protection and is
in the overriding public interest; and that the objectives of safety,
function, environmental protection and facility maintenance, based upon
sound engineering, are fully met;
10. That there are special physical circumstances or conditions
affecting the property such that the strict application of these provisions
would deprive the applicant of all reasonable use of the site in question,
and every effort to find creative ways to meet the intent of the minimum
standards has been made;
11. That the granting of the exception will not be detrimental to the
public health, welfare and safety, nor injurious to other properties in the
vicinity and/or downstream, and to the quality of receiving waters;
12. The exception is the least possible exception that could be
granted to comply with the intent of the requirements.
B. Requests for variances shall be filed in writing with the
authorized city official and shall adequately detail the basis for granting
a variance.
C. The official shall notify the city council of the intent to issue
a waiver of the requirements of this chapter as allowed by this section.
D. The decision of the official may be appealed to the city council
by any affected party by filing written notice of appeal with the city clerk
within ten days of service of the Official's decision. The cost of the
appeal shall be one hundred fifty dollars. (Ord. 2441 § 21, 1997)
Section 13.36.220 Development in critical areas.
A. Development which would increase the volume or rate of discharge
due to any storm from the subject property shall not be permitted in areas
designated as critical.
B. Proposed development located wholly or partially within critical
areas shall be reviewed with respect to policies adopted within the city
zoning ordinance.
C. Where application of the provisions of this section will deny all
reasonable uses of the property, the restriction on development contained in
this section may be waived for the subject property, provided that the
resulting development shall be subject to all the remaining terms and
conditions of this chapter. All decisions based on the provision of this
section shall be compatible with the surface water quality management plan
for the basin in which the subject property is located. For development in
areas designated as critical, the developer shall provide information
regarding volume and a rate of discharge for a range of storms as directed.
The requirements of this section shall apply regardless of any variance
under Section 13.36.210.
D. All development will comply with the city zoning ordinance
relative to development in critical areas. (Ord. 2441 § 22, 1997)
Section 13.36.230 Establishment of regional
facilities.
A. In the event that public benefits would accrue due to modification
of the stormwater plan for the subject property to better implement the
recommendations of the city's surface water quality management plan, the
authorized city official may recommend that the city should assume some
responsibility for the further design, construction, operation and
maintenance of drainage facilities receiving runoff from the subject
property. Such decision shall be made concurrently with review and approval
of the stormwater plan as specified in this chapter.
B. In the event the city decides to assume some responsibility for
design, construction, operation and maintenance of the facilities, the
developer will be required to contribute a pro rata share to the
construction cost of the facilities. The developer may be required to supply
additional information at the request of the official to aid in the
determination by the city. Guidelines for implementing this section will be
defined by the official. (Ord. 2441 § 23, 1997)
Section 13.36.240 Bonds and liability insurance
required.
A. The city is authorized to require all persons constructing
retention/detention or other drainage treatment/abatement facilities to post
surety and cash bonds.
B. Where such persons have previously posted or are required to post
other such bonds on the facility itself or on other construction related to
the facility, such persons may, with the permission of the authorized city
official and to the extent allowable by law, combine all such bonds into a
single bond; provided, that at no time shall the amount thus bonded be less
that the total amount which would have been required in the form of separate
bonds; and provided, further, that such a bond shall on its face clearly
delineate those separate bonds which it is intended to replace.
1. Construction Bond. Prior to commencing construction, the person
constructing the facility shall post a construction bond in an amount
sufficient to cover the cost of conforming the construction with the
approved drainage plans. The amount of the bond shall be increased at
one-year intervals in a proportion equivalent to the prevailing rate of
inflation in construction costs as specified in the procedures manual. After
determination by the official that all facilities are constructed in
compliance with the approved plans, the construction bond shall be released.
Alternatively, an equivalent cash deposit to an escrow account administered
by a local bank designated by the city could be required at city option.
2. Maintenance Bond. After satisfactory completion of the facilities
and concurrent with release of the construction bond by the city, the person
constructing the facility shall commence a two-year period of satisfactory
maintenance of the facility. A cash bond, to be used at the discretion of
the official to correct deficiencies in the maintenance affecting public
health, safety and welfare, must be posted and maintained throughout the
two-year maintenance period. The amounts of the cash bond shall be
determined by the official, but shall not be in excess of ten percent nor
less than five percent of the estimated construction cost of the drainage
facilities.
3. Performance Bond. A surety bond or cash bond to cover the cost of
design defects or failures in workmanship of the facilities shall also be
posted and maintained throughout the two-year maintenance period. The amount
of the bonds shall be increased at one-year intervals in a proportion
equivalent to the prevailing rate of inflation. Alternatively, an equivalent
cash deposit to an escrow account administered by a local bank designated by
the city could be required at city option.
4. Liability Policy. The person constructing the facility shall
maintain a liability policy in an amount established by the director which
shall name the city as an additional insured and which shall protect the
city from any liability up to those amounts for any accident, negligence,
failure of the facility, or any other liability whatsoever, relating to the
construction or maintenance of the facility. The liability policy shall be
maintained for the duration of the facility by the owner of the facility;
provided, that in case of facilities assumed by the city for maintenance
pursuant to Section 13.36.230 of this chapter, the liability policy shall be
terminated when and if the city maintenance responsibility commences. (Ord.
2441 § 24, 1997)
Section 13.36.250 Applicability to governmental entities.
All municipal corporations and governmental entities, unless otherwise
provided, shall submit a stormwater plan and comply with the terms of this
chapter when developing and/or improving land, including but not limited to
road building and widening, within areas of the city. (Ord. 2441 § 25, 1997)
Section 13.36.260 Other permits and requirements.
A. It is recognized that other city, county, state and federal
permits, conditions and requirements may apply to the proposed action and
that compliance with the provisions of this chapter does not constitute
compliance with such other requirements.
B. When any provision of any other chapter of the Anacortes Municipal
Code conflicts with this chapter, that provision which provides more
environmental protection shall apply unless specifically provided in this
chapter. (Ord. 2441 § 26, 1997)
Section 13.36.270 Protection of public and private rights.
Implementation of any provision of this chapter shall not cause nor be
construed as an infringement of the rights of individuals, municipalities,
or corporations other than the developer seeking a permit or approval as
described in Section 13.36.300. (Ord. 2441 § 27, 1997)
Section 13.36.280 Private maintenance of drainage
facilities.
The city council may determine through the subdivision process that a
particular subdivision design in a particular location is such that the city
will not accept ownership and/or maintenance responsibilities. In this
situation, formation of a homeowners association with maintenance and
operation responsibilities shall be mandated. (Ord. 2441 § 28, 1997)
Section 13.36.290 Enforcement, violations, and penalties.
The provisions set forth in the city zoning ordinance shall apply to all
violations of this chapter, with the authorized city official acting in the
capacity of administrator. (Ord. 2441 § 29, 1997)
Section 13.36.300 Liability.
A. Nothing contained in this chapter is intended to be nor shall be
constructed to create or form the basis for any liability on the part of the
city, or its officers, employees or agents, for any injury or damage
resulting from the failure of an owner of property or land to comply with
the provisions of this chapter, or by reason or in consequence of any
inspection, notice, order, certificate, permission or approval authorized or
issued or done in connection with the implementation or enforcement of this
chapter, or by reason of any action or inaction on the part of the city
related in any manner to the enforcement of this chapter by its officers,
employees or agents.
B. Any city employee charged with the enforcement of this chapter,
acting in good faith and without malice on behalf of the city in the
discharge of his/her duties, shall not be personally liable for any damage
that may accrue to persons or property as a result of any act required or by
reason of any act or omission in the discharge of his/her duties. Any suit
brought against an employee because of such act or omission performed by
him/her in the enforcement of any provision of this chapter shall be
defended by the city. (Ord. 2441 § 30, 1997)
Chapter 13.40 WASTEWATER COLLECTION AND TREATMENT SYSTEM
Section 13.40.010 Purpose and policy.
A. This chapter sets forth uniform requirements for industrial
discharges into the city wastewater collection and treatment system (POTW)
and enables the city to protect public health in conformity with all
applicable local, state, and federal laws relating thereto.
B. The objectives of this chapter are:
1. To prevent the introduction of pollutants into the city's POTW
which will interfere with the normal operation of the system or contaminate
the resulting sludge;
2. To prevent the introduction of pollutants into the city's POTW
which do not receive adequate treatment, and which will pass through the
system into receiving waters or the atmosphere or otherwise be incompatible
with the system; and
3. To improve the opportunity to recycle and reclaim wastewater and
sludge from the system.
C. This chapter provides for the regulation of discharges into the
POTW through the enforcement of administrative regulations.
D. This chapter shall apply to the city and to all industrial users
within and outside the city who are, by contract or agreement with the city,
dischargers to the Anacortes POTW. This chapter is a supplement to Ordinance
No. 1150 codified in Chapter 13.08 of this code. (Ord. 1945 § 1.1, 1984)
Section 13.40.020 Definitions.
For the purpose of this chapter, the following words shall have the
following meanings:
A. "Act" or "The Act" means the Federal Water Pollution Control Act,
also known as the Clean Water Act, as amended, 33 U.S.C. 1251, et seq.
B. "Applicable pretreatment standards" means for any specified
pollutant, the city's prohibitive discharge standard, city's specific
limitation on discharge, the state of Washington pretreatment standard, or
the National Categorical Pretreatment Standard (when effective), whichever
is most stringent or applies at the time of issuance of an Industrial
Wastewater Acceptance Form (IWA).
C. "City" means the city of Anacortes, through the Anacortes city
council.
D. "Categorical pretreatment standards" means national pretreatment
standards specifying quantities or concentrations of pollutant or pollutant
properties which may be discharged or introduced into a POTW by specific
industrial dischargers.
E. "Director" means the person designated by the city to supervise
operation of the POTW and who is charged with certain duties and
responsibilities by this chapter, or his duly authorized representative.
F. "EPA" means the United States Environmental Protection Agency.
G. "Industrial discharger/user" means any nonresidential user who
discharges an effluent into a POTW by means of pipes, conduits, pumping
stations, force mains, constructed drainage ditches, intercepting ditches,
and all constructed devices and appliances appurtenant thereto.
H. "Industrial waste" means solid, liquid or gaseous waste resulting
from any industrial, manufacturing, trade, or business process or from the
development, recovery or processing of natural resources.
I. "Interference" means the inhibition or disruption of a POTW's
treatment processes or operations which is a cause of or significantly
contributes to either a violation of any requirement of its NPDES permit or
to the prevention of sewage sludge use or disposal by the POTW in accordance
with all local, state and federal regulations or permits.
J. "New source" means any building, structure, facility, or
installation from which there is or may be a discharge, the construction of
which commenced:
1. After promulgation of pretreatment standards under Section 307(c)
of the Federal Act which are applicable to such source; or
2. After proposal of pretreatment standards in accordance with
Section 307(c) of the Act which are applicable to such sources, but only if
the standards are promulgated in accordance with Section 307(c) within one
hundred twenty days of their proposal.
K. "NPDES" means the National Pollutant Discharge Elimination System
permit program of the EPA pursuant to Section 402 of the Act (330 U.S.C.
1342).
L. "Pretreatment" means the reduction of the amount of pollutants,
the elimination of pollutants, or the alteration of the nature of pollutant
properties in wastewater to a less harmful state prior to or in lieu of
discharging or otherwise introducing such pollutants into a POTW.
M. "Pretreatment requirements" means any substantive or procedural
requirement related to pretreatment, other than a national pretreatment
standard imposed on an industrial user.
N. "Publicly owned treatment works" (POTW) means any sewage treatment
works and the sewers and conveyance appurtenances discharging thereto,
owned, and operated by the city.
O. "Shall" is mandatory: "May" is permissive.
P. "Significant industrial discharger/user" means any industrial
discharger/user of the city's POTW who:
1. Is subject to or potentially subject to national pretreatment
standards promulgated under Section 307(b) or (c) of the Clean Water Act;
2. Contains in their wastes any significant quantities of toxic
pollutants as defined pursuant to Section 307 of the Clean Water Act;
3. Has an average daily flow five percent of the daily average flow
for the previous month in the city's POTW; or
4. Is determined by the city to have a significant impact or
potential for significant impact, either singly or in combination with other
contributing industries, on the POTW, the quality of sludge, the system's
effluent quality, or air emissions generated by the system.
Q. "Sludge load" means any substance released in a discharge at a
rate and/or concentration which causes interference to standard operation or
use of a POTW.
R. "State" means the state of Washington.
S. "Toxic pollutant" means those substances listed in the federal
priority pollutant list and any other pollutant or combination of pollutants
listed as toxic in regulations promulgated by the administrator of the
Environmental Protection Agency under Section 307 of the Clean Water Act.
T. "Upset" means an exceptional incident in which a discharger
unintentionally and temporarily is in a state of noncompliance with the
standards set forth in Appendices A and B attached to the ordinance codified
in this chapter due to factors beyond the reasonable control of the
discharger, and excluding noncompliance to the extent caused by operational
error, improperly designed treatment facilities, inadequate treatment
facilities, lack of preventive maintenance, or careless or improper
operation thereof.
U. "Wastewater" means the liquid and water-carried industrial or
domestic wastes from dwellings, commercial buildings, industrial facilities,
and institutions, together with any groundwater, surface water, and storm
water that may be present, whether treated or untreated, which is
contributed into or permitted to enter the POTW. (Ord. 1945 § 1.2, 1984)
Section 13.40.030 Abbreviations.
The following abbreviations shall have the designated meanings for the
purpose of this chapter:
BOD Biochemical oxygen demand
CFR Code of Federal Regulations
COD Chemical oxygen demand
EPA Environmental Protection Agency
l Liter
mg Milligrams
mg/l Milligrams per liter
NPDES National Pollutant Discharge Elimination System
POTW Publicly owned treatment works
SIC Standard Industrial Classification
SWDA Solid Waste Disposal Act, 42 U.S.C. 6901, et seq.
USC United States Code
TSS Total suspended solids
(Ord. 1945 § 1.3, 1984)
Section 13.40.040 General discharge prohibitions.
No industrial user shall contribute or cause to be discharged, directly
or indirectly, any of the following described substances into the city's
POTW:
A. Any liquids, solids or gases which by reason of their nature or
quantity are, or may be, sufficient either alone or by interaction with
other substances to cause fire or explosion or be injurious or hazardous in
any other way to the POTW or to the operation of the POTW. Such materials
include, but are not limited to, gasoline, kerosene, naphtha, benzene,
toluene, xylene, ethers, alcohols, ketones, aldehydes, peroxides, chlorates,
perchlorates, bromates, polychlorinated biphenyls, polybrominated biphenyls,
carbides, hydrides, stoddard solvents, and sulfides;
B. Solid or viscous substances which may cause obstruction to the
flow in a sewer or other interference with the operation of the POTW such
as, but not limited to: grease, garbage with particles greater than one-half
inch in any dimension, animal guts or tissue, paunch manure, bones, hair,
hides or fleshings, entrails, whole blood, feathers, ashes, cinders, sand,
spent lime, stone or marble dust, metal, glass, hops, waste paper, wood,
plastics, gas, tar, asphalt residues, residues from refining, or processing
of fuel or lubricating oil, mud, or glass grinding or polishing wastes;
C. Any wastewater having a pH less than 5.0 or having any other
corrosive property capable of causing damage or hazard to structures,
equipment, or personnel of the POTW;
D. Any wastewater containing toxic pollutants in sufficient quantity,
either singly or by interaction to insure or interfere with any wastewater
treatment process, constitute a hazard to humans or animals, or to exceed
the limitation set forth in the National Categorical Pretreatment Standards;
E. Any substance which may cause the POTW's effluent or treatment
residues, sludges, or scums, to be unsuitable for reclamation and reuse or
to interfere with the reclamation process. In no case shall a substance
discharged to the system cause the POTW to be in noncompliance with sludge
use or disposal criteria, guidelines or regulations developed under Section
405 of the Act; any criteria, guidelines, or regulations affecting sludge
use or disposal developed pursuant to the Solid Waste Disposal Act, the
Clean Air Act, the Toxic Substances Control Act, or state criteria
applicable to the sludge management method being used;
F. Any substance with objectionable color not removed in the
treatment process, such as, but not limited to, dye wastes and vegetable
tanning solutions;
G. Any wastewater having a temperature which will inhibit biological
activity in the POTW treatment plant resulting in interference; but in no
case, wastewater with a temperature at the introduction into the POTW which
exceeds 40°C (104°F);
H. Any slug load, which shall mean any pollutant, including oxygen
demanding pollutants (BOD, etc.), released in a single extraordinary
discharge episode of such volume or strength as to cause interference to the
POTW;
I. Any wastewater containing any radioactive wastes or isotopes of
such halflife or concentrations as exceed limits established in compliance
with applicable state or federal regulations;
J. Any wastewater which in the opinion of the director causes a
hazard to human life or creates a public nuisance. (Ord. 1945 § 2.1, 1984)
Section 13.40.050 National categorical pretreatment
standards.
National categorical pretreatment standards as promulgated by the EPA
pursuant to the Act shall be met by all industrial users of the regulated
industrial categories. (Ord. 1945 § 2.2, 1984)
Section 13.40.060 State requirements on discharges to the
POTW.
State requirements and limitations on discharges to the POTW shall be
met by all industrial users which are subject to such standards in any
instance in which they are more stringent than federal requirements and
limitations or those in this chapter or any other applicable ordinance. (Ord.
1945 § 2.3, 1984)
Section 13.40.070 Accidental discharges--Protection
procedures.
A. Each industrial user shall provide protection from accidental
discharge of prohibited or regulated materials or substances established by
this chapter. Where necessary, facilities to prevent accidental discharge of
prohibited materials shall be provided and maintained at the user's cost and
expense. Detailed plans showing facilities and operating procedures to
provide this protection shall be submitted to the city for review, and shall
be approved by the city before construction of the facility.
B. Each significant industrial user (SID), where requested by the
director, shall complete its plan and submit same to the city within one
hundred eighty days of receiving pretreatment program approval. No user who
discharges to a POTW after the aforesaid date shall be permitted to
introduce pollutants into the system until accidental discharge protection
procedures have been approved by the city. Review and approval of such plans
and operating procedures by the director shall not relieve the user from the
responsibility to modify its facility as necessary to meet the requirements
of this chapter. (Ord. 1945 § 2.4.1, 1984)
Section 13.40.080 Accidental discharges--Notification.
Industrial users shall notify the city immediately upon the occurrence of a
slug load or accidental discharge of substances prohibited by this chapter.
The notification shall include location of discharge, date and time thereof,
type of waste, concentration and volume, and corrective actions. Any user
who discharges slugs of prohibited materials shall be liable for any
expense, loss or damage to the POTW, in addition to the amount of any fines
imposed by the city on account thereof under state or federal law. (Ord.
1945 § 2.4.2, 1984)
Section 13.40.090 Pretreatment--General.
Significant industrial users shall provide necessary wastewater
pretreatment as required to comply with this chapter and shall achieve
compliance within the time limitations specified by the city. Any
facilities required to pretreat wastewater to a level acceptable to the
city shall be provided, operated, and maintained at the user's expense.
(Ord. 1945 § 2.5.1, 1984)
Section 13.40.100 Pretreatment--Facility plans.
Detailed plans showing the pretreatment facilities and operating
procedures shall be submitted to the Director for review, and must be
acceptable to the city prior to commencement of discharge from the facility.
The review of such plans and operating procedures will in no way relieve the
user from the responsibility of modifying its facility as necessary to
produce an effluent acceptable to the city under the provisions of this
chapter. (Ord. 1945 § 2.5.2, 1984)
Section 13.40.110 Pretreatment--Changes in pretreatment
plans.
Any subsequent changes in the pretreatment facilities or methods of
operation shall be reported to and be acceptable to the city prior to the
user's initiation of the changes. (Ord. 1945 § 2.5.3, 1984)
Section 13.40.120 Dilution.
No industrial user shall increase the use of potable or process water in
any way for the purpose of diluting a wastewater discharge as a partial or
complete substitute for adequate treatment to achieve compliance with the
standards set forth in this chapter. (Ord. 1945 § 2.6, 1984)
Section 13.40.130 Right of revision.
The city reserves the right to amend the ordinance codified in this
chapter to provide for more stringent limitations or requirements on
discharges to the POTW where deemed necessary to comply with the objectives
set forth in Section 13.40.010. (Ord. 1945 § 2.7, 1984)
Section 13.40.140 Supplementary limitations.
(Reserved) Heavy metals limits. (Ord. 1945 § 2.8, 1984)
Section 13.40.145 Heavy metals limits.
LOCAL LIMITS FOR HEAVY METALS
AND CYANIDE
All concentrations are in milligrams per liter
(mg/l = ppm)
Daily Grab
Average Max Sample Max
Substance Concentration Concentration
Arsenic 0.5 3.0
Cadmium 0.5 0.5
Chromium 2.75 4.0
Copper 3.0 6.0
Cyanide 2.0 2.5
Lead 2.0 3.0
Mercury 0.1 0.2
Nickel 2.5 4.0
Silver 1.0 2.0
Zinc 5.0 8.0
pH 5.5 - 12 5.5 - 12
Oil/Grease 75.0 75.0
(Ord. 2282, 1993: Ord. 1945 § 2.8.1, 1984)
Section 13.40.150 Fees and charges--Purpose.
It is the purpose of this section and Section 13.40.160 to provide for
the recovery of costs from industrial users of the city's POTW to compensate
for the implementation and administration of the pretreatment program
established in this chapter. (Ord. 1945 § 3.1, 1984)
Section 13.40.160 Fees and charges--Generally.
A. The city may adopt charges and fees which may include:
1. Fees for monitoring, inspections, and surveillance procedures;
2. Fees for reviewing accidental discharge procedures and
construction;
3. Other fees as the city may deem necessary to carry out the
requirements contained in this chapter.
B. These fees relate solely to the matters covered by this chapter
and are separate from all other fees chargeable to the city. (Ord. 1945 §
3.2, 1984)
Section 13.40.170 Wastewater discharges.
It is unlawful to discharge any wastewater to any sewer outlet within
the jurisdiction of the city and/or to the POTW except as authorized by the
director in accordance with the provisions of this chapter. In addition to
the terms of this chapter, a significant industrial discharger shall not be
allowed to connect to the city's POTW without written approval from the
director. (Ord. 1945 § 4.1, 1984)
Section 13.40.180 Wastewater discharge data
disclosure--Generally.
All industrial users proposing to connect to or to discharge wastewater
to the POTW shall comply with all terms of this chapter. (Ord. 1945 § 4.2.1,
1984)
Section 13.40.190 Wastewater discharge data--Disclosure
forms.
A. All significant industrial users (SIDs) shall complete and file
with the director a disclosure declaration in the form prescribed by the
city. Existing SIDs shall file disclosure forms within sixty days after the
city receives pre-treatment program authority and proposed