Board denies appeal on T Bailey Project

Anacortes American, Wednesday, October 16, 2002

By Nancy Walbeck

American Staff Writer

 

The company proposing a steel-fabrication plant on South March Point Road and one of the environmental groups asking for protection for an adjacent heronry say they will continue discussing a possible settlement, despite a ruling Thursday that threw out two appeals related to the firm’s grading permit.

The city’s board of adjustment ruled Thursday, Oct. 10, that Skagit Land Trust and several other environmental groups failed to file the permit appeal before the deadline.  Written findings will be available Thursday, and trust officials and others say they will consider appealing that decision to Superior Court.

“We also will wait for the building permit to come out, and likely will appeal that,” Brenda Cunningham, land specialist for Skagit Land Trust, said.

T Bailey is proposing a steel-fabrication plant on South March Point Road that will be built near a heronry.  The board ruling means T Bailey can continue to clear and grade its site.  And city officials said a building permit likely will be issued this week.

But T Bailey and the trust also say they are continuing to discuss several issues at the site, including a monitoring plan and a possible re-negotiation of the Port’s lease with T Bailey.

Cunningham said the Port could provide a conservation easement or some other mechanism to provide more forest area for the herons, which T Bailey owner Gene Tanaka says means a new leasing contract is necessary.

An agreement between T Bailey and the trust also would include the trust convincing the other environmental groups to drop their appeals.  However, Tom Glade of Evergreen Islands, said that would depend on what T Bailey and the trust agree on, and whether the other environmental groups can accept those terms.

At the Thursday meeting, the Anacortes board of adjustment ruled that both groups failed to file their appeal before the deadline.

The Skagit Land Trust and a second group, which includes Evergreen Islands and the Skagit Audubon Society, among others appealed the city’s clearing and grading permit issued to T Bailey. The firm, already doing work at two other locations, is planning to relocate to 9268 South March Point Road, adjacent to property with a heronry with more than 400 nests.  Skagit Land Trust largely owns and oversees the property where the heronry is located.

In a 2-1 ruling, the board of adjustment decided the land trust and the second group of environmental organizations missed the deadline, despite some discussion that they might have been mislead by the city’s building department staff.  But sworn testimony Thursday from city building official Ed Frank and city plans examiner Don Measamer disputed that

“When you miss the appeal period, you miss it.” Craig Magnusson, the Seattle attorney representing T Bailey, said.

But David Mann, representing Skagit Land Trust, argued that the groups had 14 days from the date the permit was issued Aug. 13 and hand delivered by Measamer to T Bailey.  Magnusson said no, city ordinance calls for a 10-day period to respond, and the trust and other clearly missed that “window” of opportunity.

The five-member board of adjustment, appointed by the mayor and approved by city council, usually hears street vacations, yard setbacks and the like.  Ken Wilson, George Mehler, Gary Coatney and John Curtis are board members, along with chair Brad Snyder.

On Thursday, Wilson was absent and Mehler was challenged by Magnusson, primarily because he is a member of Skagit Land Trust.  Coatney and Curtis voted for denial, while Snyder voted against.

Following the hearing, City Planning Director and City Attorney Ian Munce confirmed the city will issue the building permit this week, which makes the ruling on the grading permit moot at this point.

Even though the two appeals urged the city to issue a stop-work order, Munce and the city’s Seattle attorney, Steve DiJulio, advised city council not to, because the city could be liable under its ordinances.

“When we issue a building permit, that will trigger a whole new appeal back to the board of adjustment,” Munce said.

Meanwhile DiJulio will write a draft order for the board of adjustment, which will then be reviewed at a special meeting at 7 p.m. Oct. 17 in City Hall Chambers.